Surface Abandonment Proposal

Remote Cut & Cap
Pouce Coupe
100/14-14-076-12W6

Prepared for CANLIN Energy. A field-ready plan for surface abandonment of a remote wellbore — portable ultra-high-pressure cutting unit, staged from Canlin's road-accessible location 1.2 km south-east of the lease.

0

Wellbore

Cut & cap scope

0.0mm

Surface Casing

53.6 kg/m J-55

0.0mm

Production Casing

23.1 kg/m K-55

0

Project Days

Including mob / demob

View Rate ScheduleContacts

01 — Project Area

Two-Area Footprint

A road-accessible staging area and a remote wellbore, linked by a short overland route that will be confirmed by Canlin's lease operator.

Staging Area

100/01-14-076-12 W6M

Road access

Canlin road-accessible location used for equipment offload, crew marshalling and trailer parking.

Remote Well

100/14-14-076-12 W6M

Cut & cap

Approximately 1.2 km north and 0.5 km west of staging. Conductor barrel present at surface.

Staging 01-14~1.7 km overlandWellbore 14-14

02 — Well Details

Wellbore & Configuration

Casing programme and surface conditions as provided by Canlin for the remote wellbore.

Surface Casing

244.5 mm x 53.6 kg/m J-55 surface casing to be cut below grade and capped to regulation.

Production Casing

139.7 mm x 23.1 kg/m K-55 production casing, cut concentrically in the same program.

Conductor Barrel

A conductor barrel is present and will be addressed as part of the surface cut sequence.

Site Condition

Photographs supplied are from 2020; the lease will be materially more overgrown today.

03 — Access

Field Access Scenarios

Four possible outcomes from the quad assessment. Each drives a different equipment spread and brushing scope.

1

Minimal Brushing

A narrow path can be woven into the wellsite with a small clearing immediately adjacent to the wellbore.

2

Significant Brushing

A path and a well-centre clearing must be cut to allow equipment and crew onto the location.

3

Portable

Access and wellsite are heavily treed, making a portable cut-and-cap system the practical option.

4

Brushing Crew

Ground access is feasible but a dedicated brushing crew prepares the route and wellsite beforehand.

Site photographs date from 2020

Vegetation will have advanced significantly. Access method, brushing requirements and schedule are confirmed only after the lease operator assessment is returned.

Lease Operator Assessment

Canlin is dispatching a lease operator by quad to confirm access.

Equipment Selection

The portable equipment spread is confirmed from that assessment.

Pricing Confirmation

Access scope drives brushing costs and final mobilization line items.

04 — Approach

Our Method

How a portable spread compares with a conventional access-first abandonment on a remote, overgrown lease.

ConsiderationStandard ApproachInnovative Well Abandonment
Cutting methodTrack-mounted mechanical cutter requiring full lease accessRemote portable ultra-high-pressure cutting unit, packable to the wellbore
Site disturbanceWide access road and full lease clearingNarrow path with a small clearing at well centre where conditions allow
Remote contingencyProject deferred until a road can be builtPortable spread available if the lease proves impassable
StagingNew staging pad constructed near the wellboreExisting Canlin road-accessible location at 01-14 used as staging

Cutting method

Standard

Track-mounted mechanical cutter requiring full lease access

Our approach

Remote portable ultra-high-pressure cutting unit, packable to the wellbore

Site disturbance

Standard

Wide access road and full lease clearing

Our approach

Narrow path with a small clearing at well centre where conditions allow

Remote contingency

Standard

Project deferred until a road can be built

Our approach

Portable spread available if the lease proves impassable

Staging

Standard

New staging pad constructed near the wellbore

Our approach

Existing Canlin road-accessible location at 01-14 used as staging

05 — Rates

Equipment & Rate Schedule

Itemized project estimate showing the supplied units, quantities, rates and extended totals.

Primary Equipment

HP Pumping System

$9,000.00

Day × 3 at $3,000.00

$2,500.00

5 Tonne Excavator

Weekly × 1 at $2,500.00

$2,500.00

Tracked Skid Steer

Weekly × 1 at $2,500.00

$1,750.00

Side by Side

Weekly × 1 at $1,750.00

$1,000.00

40' Trailer

Weekly × 1 at $1,000.00

$2,500.00

Skid - Custom built for portable unit

One time × 1 at $2,500.00

$1,500.00

Tooling

One time × 1 at $1,500.00

Logistics & Mobilization

  • Support Truck #1

    Hourly × 28 at $25.00

    $700.00

  • Support Truck #2

    Hourly × 28 at $25.00

    $700.00

  • Support Truck Mobilization

    KM × 645 at $1.75

    $1,128.75

  • Support Truck Demobilization

    KM × 645 at $1.75

    $1,128.75

  • Subsistence

    Day × 6 at $275.00

    $1,650.00

Crew Labour

  • Project Manager

    Hourly × 28 at $140.00

    $3,920.00

  • Supervisor 1

    Hourly × 28 at $120.00

    $3,360.00

  • Operator 1

    Hourly × 28 at $100.00

    $2,800.00

  • Prep

    Hourly × 10 at $140.00

    $1,400.00

Estimated Project Total

Based on the units and quantities listed above.

$37,537.50

06 — Assumptions

Assumptions & Conditions

The basis of estimate for this proposal, including access, schedule and operating conditions.

Access Method

Final access and brushing scope follow Canlin's lease operator assessment. Pricing is adjusted once the access method is confirmed.

Staging Area

Canlin's road-accessible location at 100/01-14-076-12W6 is used for staging, approximately 1.2 km and 0.5 km offset from the wellbore.

Rates & Surcharges

Rates are quoted without fuel surcharge unless otherwise directed. Standard daylight operating hours apply. There will be no overtime.

Estimate Basis

The project estimate is based on the units, quantities and rates listed in the supplied schedule, including mobilization and demobilization.

Site Condition

Photographs are from 2020. Actual vegetation and ground conditions will differ and may affect schedule and cost.

Regulatory Scope

Work covers surface abandonment — cut and cap — of the identified wellbore only. Downhole abandonment is excluded.

07 — Contacts

Contacts & Next Steps

Leads on both sides of the project, and what has to close before the crew mobilizes.

Innovative Well Abandonment logo

Innovative Well Abandonment

Contractor

Scott Bowes portrait

Scott Bowes

President — Primary Contact

780-808-1349sbowes@innovativewa.com
Chris Hamilton portrait

Chris Hamilton

Business Development Manager

403-630-1243chamilton@innovativewa.com
CANLIN Energy logo

CANLIN Energy

Client — 2701 237 4th Ave SW, Calgary, Alberta

GT

Geoff Tempany

Abandonment Consultant

403-801-2654geoff.tempany@canlinenergy.com

Project Photos

Gated access road to the project site
Overgrown trail leading into the project site
Well head surrounded by trees and brush
Next Step

Confirm access, approve estimate, mobilize

Awaiting Canlin's lease operator assessment to lock the access method and brushing scope, then estimate approval before scheduling the crew.

01

Assessment

02

Approval

03

Mobilize